21
"Calculate re-order level from the following:
Safety stock: 1000 units
Consumption per week: 500 units
It takes 12 weeks to reach material from the date of ordering"
Safety stock: 1000 units
Consumption per week: 500 units
It takes 12 weeks to reach material from the date of ordering"
Answer & Solution
Answer: Option
D
Solution:
Re-order level = Safety stock + Total consumption
= 1000 + (500 × 12) = 1000 + 6000 = 7000 units.
= 1000 + (500 × 12) = 1000 + 6000 = 7000 units.