ExamVeda
Login
Home
41
Both Rowan plan and 50-50 Halsey plan will provide the same earning when the actual time is _________ the standard time.
Discuss
Answer & Solution
Answer: Option B
Solution:
Both Rowan plan and 50-50 Halsey plan will provide the same earning when the actual time is One-half the standard time.
42
Critical Path Net Work helps an engineer
Discuss
Answer & Solution
Answer: Option D
Solution:
Critical Path Net Work helps an engineer
- To concentrate his attention on critical activities
- To divert the resources from noncritical advanced activities to critical activities
- To be cautious for avoiding any delay in the critical activities to avoid delay of the whole project
43
Queueing theory is used for
Discuss
Answer & Solution
Answer: Option D
Solution:
Queueing theory is used for
- Inventory problems
- Traffic congestion studies
- Job-shop scheduling
44
Percent idle time for men or machines is found by
Discuss
Answer & Solution
Answer: Option A
Solution:
Percent idle time for men or machines is found by work sampling.
45
A critical activity has
Discuss
Answer & Solution
Answer: Option C
Solution:
A critical activity has Zero slack
46
The critical activity has
Discuss
Answer & Solution
Answer: Option C
Solution:
The critical activity has Zero float
47
In order that linear programming techniques provide valid results
Discuss
Answer & Solution
Answer: Option C
Solution:
In order that linear programming techniques provide valid results
- Relations between factors must be linear (positive)
- Relations between factors must be linear (negative)
48
Standard time is defined as
Discuss
Answer & Solution
Answer: Option A
Solution:
Standard time is defined as Normal time + allowances
49
In a PERT chart
Discuss
Answer & Solution
Answer: Option A
Solution:
In a PERT chart All activities should be numbered
50
Slack of various events on the critical path in PERT/CPM chart
Discuss
Answer & Solution
Answer: Option C
Solution:
Slack of various events on the critical path in PERT/CPM chart Remain constant