11
If sales budget variance is $57000 and flexible budget amount is $97000, then static budget amount will be
Answer & Solution
Answer: Option
A
Solution:
Static budget = Flexible budget - Sales budget variance
= $97000 - $57000 = $40,000
= $97000 - $57000 = $40,000