In steel plant the most important system for materials handling is
Discuss
Answer & Solution
Answer: Option D
Solution:
In steel plant the most important system for materials handling is Locos
62
Work study involves
Discuss
Answer & Solution
Answer: Option C
Solution:
Work study involves Method study and work measurement
63
Gantt chart provides information about the
Discuss
Answer & Solution
Answer: Option C
Solution:
A Gantt chart is a type of bar chart that illustrates a project schedule.
This chart lists the tasks to be performed on the vertical axis, and time intervals on the horizontal axis.
The width of the horizontal bars in the graph shows the duration of each activity.
64
Pick up the correct statement from the following
Discuss
Answer & Solution
Answer: Option D
Solution:
- If the float is positive and the activity is delayed by a period equal to its total float, the completion of project in not delayed
- If the float of an activity is negative, delay in its performance is bound to delay the completion of project
- If the float of an activity is zero, the activity is critical and any delay in its performance will delay the whole project
65
Pick up the correct statement from the following
Discuss
Answer & Solution
Answer: Option D
Solution:
Program evaluation and review technique (PERT) is a technique adopted by organizations to analyze and represent the activity in a project,
and to illustrate the flow of events in a project.
PERT is a method to evaluate and estimate the time required to complete a task within deadlines.
66
Pick up the correct statement from the following
Discuss
Answer & Solution
Answer: Option D
Solution:
- Critical path method is an improvement upon bar chart method.
- Critical path method provides a realistic approach to the daily problems.
- Critical path method avoids delays which are very common in bar chart.
67
Pick up the incorrect statement from the following
Discuss
Answer & Solution
Answer: Option D
Solution:
- An activity of the project is denoted by an arrow on the net work.
- The tail of the arrow indicates the start of the activity.
- The head of the arrow indicates the end of the activity.
68
Routing
Discuss
Answer & Solution
Answer: Option A
Solution:
Routing decides the path and sequence of operations to be performed on the job from one machine to another.
Routing in production management is related to considerations of layout, temporary storage of in-process inventory and material handling.
69
PERT is applied for
Discuss
Answer & Solution
Answer: Option D
Solution:
PERT is applied for
- Marketing programmes and advertising programmes
- Installation of machinery
- Research and development of products
70
Discrepancies of bar chart techniques are
Discuss
Answer & Solution
Answer: Option D
Solution:
Discrepancies of bar chart techniques are
- Consequential effects of lack in one activity on the finish date
- Free time available for an activity can't be predicted
- Effective monitoring/controlling can't be done